City increases debt to fund wastewater extension project

Originally Posted on Daily Emerald via UWIRE

Eugene City Council unanimously approved an additional loan and contract that will increase the city’s debt by around $550,000 during the council meeting on Sept. 28. 

The loan comes from the Clean Water State Revolving Fund by the Oregon Department of Environmental Quality and will be used to fund a wastewater extension project.

The project was initially estimated to cost $1.65 million, but the total loan amount has increased to approximately $2.2 million. This led to the city taking on an additional $550,000 of debt to recover the additional principal forgiveness, which is 50% of the loan amount, or $1.1 million. 

“The city intends to pay back the low-interest loan as soon as possible,” Rachael Vaicunas, a principal city engineer with the city of Eugene, said in an email statement to The Daily Emerald. “The impact of increasing the debt is the additional principal forgiveness amount.”

Principal forgiveness reduces the amount of money a borrower is required to repay on a loan. The city of Eugene has budgeted $1.1 million from wastewater utility fees and system development charges to go towards this project.

Vaicunas said that the project got more expensive because the construction cost went up since the time the original estimate was developed.

“As we got into the design details that include temporary pedestrian access during construction and dewatering of a deep trench, it was clear it would be more expensive than originally thought,” Vaicunas said. “We are lucky and grateful for the (Oregon Department of Environmental Quality Clean Water State Revolving Fund) program.”

The Prairie Road South of Beltline Highway Wastewater Extension project extends from north of Bushnell Lane to north of Maxwell Road. The city wants to extend the wastewater system along Prairie Road by constructing new wastewater pipes and manholes for roughly 27 industrial-zone properties, which will stretch approximately 84 acres. 

The project is identified in the Major Collection System Expansion section in the city’s 2020 Wastewater Master Plan. 

Vaicunas said that the project will make wastewater service available to properties that currently have septic tanks, or underground wastewater treatment structures. Decommissioning private septic systems will eliminate potential sources of contamination to groundwater, which is vital because the groundwater in this location feeds into the Willamette River. 

Traffic impacts on the public while the project is undergoing construction are expected, according to Vaicunas. Marion Suitor, Eugene’s public affairs manager, said the project’s construction dates are not yet known. 

The post City increases debt to fund wastewater extension project appeared first on Daily Emerald.